Assembly of the first Tranche 3 Typhoon, destined for delivery to the Royal Air Force, has now been completed together with initial testing.
The aircraft, British single seat no 116, has now entered electromagnetic testing.
A range of Typhoon systems such as the armament, fuel and flight controls could be susceptible to radio frequency transmissions such as ground radars or TV and radio transmission masts.
To ensure the aircraft will operate correctly and safely in flight when exposed to these threats, the aircraft is undergoing Electromagnetic Compatibility (EMC) testing through a technique known as Direct Current Injection. This means the aircraft is injected with simulated threat signals directly into specially designed points on the nose, tail and wing tips.
EMC testing will last around eight weeks, after which the aircraft will undergo avionics testing before progressing to engine ground runs.
Under the Tranche 3A contract signed in 2009, a total of 112 aircraft have been ordered for the four European partner nations of Germany, Italy, Spain and the UK, with 40 aircraft bound for the Royal Air Force.
Deliveries of Tranche 3 Typhoons are expected to start later this year.
Tranche 3 Typhoon Completed with Initial Testing
18.03.2013 Europe
Latest news
Latest events
Middle East Special Operations Commanders Conference (MESOC)
26 Oct 2026Aqaba - JordanSpecial Operations Forces Exhibition (SOFEX 2026)
27 - 29 Oct 2026Aqaba International Exhibition & Convention Center - JordanEURONAVAL 2026
03 - 06 Nov 2026Paris Nord Villepinte - France4th Saudi International Maritime Forum
23 - 25 Nov 2026Sofitel Riyadh Hotel & Convention Center - Saudi Arabia